2017-02-21
In December, Alain Daniel, Project Manager – Maintenance, and Nicolas Goyer, External Consultant, kicked off civil works for the installation of a generator and modifications to the building’s main distribution. The generator’s duct banks and blinding slab have been completed and work will continue once the equipment on order has been received. The delivery of major equipment is expected by the end of the month and the project should be wrapping up at the end of May.