2015-10-09
The ABB Vaudreuil project is making very good progress. Dejan Karadeglija, Jean-Pierre Renaud and thirty workers are currently performing the last phase of our BMS work. The connections in the control boxes, and tests performed on all cables, are progressing well. Calibration of equipment has started in collaboration with our partner Systemex Industries. Systemex Automation, another partner, is also present on the project site to help with the manufacturing of panels and cable termination. Work should be comleted by December.